DAR-2021-000927
SPT/Katomei to Don Bosco/72
Improvement of road Katomei to Don Bosco Convent - 1.5 kms (SH:- WBM & PC).
2020-03-17
PWD
Senapati
26.00
5.00
State Plan
75%
First
25.280154622940927,94.02478871468051
WBM & PC.
Progress Update : 2021-03-13
75%
First
eesptd
25.280154622940927,94.02478871468051
25.2752606,94.022774
0.58064413757645
Approved
0
1.Name of work:- Improvement of Road from Katomei to Don Bosco convent- 1.5kms Physical progress of the work Financial break-up Physical progress 1) WBM 30.85% 90% 2) PC 69.15% 70%

Progress Update : 2021-03-13
75%
First
eesptd
25.280154622940927,94.02478871468051
25.2747724,94.0186681
0.85839348250571
Approved
2021-03-15 07:38:04
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) WBM 30.85% 90% 2) PC 69.15% 70%

Progress Update : 2021-03-13
75%
First
eesptd
25.280154622940927,94.02478871468051
25.3284171,94.0530987
6.0741492924594
Approved
2021-03-15 07:39:44
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) WBM 30.85% 90% 2) PC 69.15% 70%