DAR-2017-000100
MID-NEC-LANGATHEL
Construction of Mini Barrage a/c Langathel River nearby Lamlong Khunou, Thoubal District
16/10/2017
Minor Irrigation Department
Thoubal
400.00
100
NEC
Ongoing
1
24.52,94.076
Construction of Pick-up Weir, Side Wall, Protection Work for the Weir and lined canal to create irrigation potential 700 Ha.
Progress Update : 09/07/2019
Ongoing
1
midtbl01
24.52,94.076
24.5387359,94.0582078
2.7530018918605
100
Pick up weir constructed across Langathel river and its canal

Progress Update : 29/12/2017
Ongoing
1
midtbl01
24.52,94.076
24.5220297,94.075902
0.22589911800467
0
Construction of Pick Up Weir (foundation)

Progress Update : 29/12/2017
Ongoing
1
midtbl01
24.52,94.076
24.5220166,94.0759312
0.22433288605357
0
Construction of Pick Up Weir (foundation)

Progress Update : 29/12/2017
Ongoing
1
midtbl01
24.52,94.076
24.5219701,94.0760721
0.21917599997503
0
Construction of Pick Up Weir (foundation)

Progress Update : 15/12/2017
On going
1
midtbl01
24.52,94.076
24.5221052,94.0759914
0.23407791162494
0
Construction of Pick up Weir ( pile foundation)

Progress Update : 15/12/2017
On going
1
midtbl01
24.52,94.076
24.5221052,94.0759914
0.23407791162494
0
Construction of Pick up Weir

Progress Update : 06/12/2017
Ongoing
1
midtbl01
24.52,94.076
24.5495725,94.0307991
5.6316843448379
0
Construction of Pick up Weir (leveling)

Progress Update : 06/12/2017
Ongoing
1
midtbl01
24.52,94.076
24.5220986,94.0760964
0.2335461515635
0
Construction of Pick up Weir (leveling)