DAR-2021-000901
TML/Tamah Village-IT/49
Constn. of road from Tamah Village to IT road - 5Km
2020-03-16
PWD
Tamenglong
130.00
35
State Plan
On going
NA
25.17230391537764,93.7118213081093
Progress Update : 2021-03-09
On going
NA
eetmld
25.17230391537764,93.7118213081093
25.1587112,93.6818154
3.3767788927557
Approved
2022-09-28 08:49:29
pwdse2ce
35
SL.No. Item Physical Progress 1 E/ W in hill cutting Completed 2 Kutcha Drain Completed 3 Preparing sub- Grade Completed 4 GSB In progress 5 900 mm Dia. Pipe culvert In progress

Progress Update : 2021-03-09
On going
NA
eetmld
25.17230391537764,93.7118213081093
25.1597978,93.6827664
3.2377647264941
Approved
2021-11-02 10:15:10
pwdse2ce
0
SL.No. Item Physical Progress 1 E/ W in hill cutting Completed 2 Kutcha Drain Completed 3 Preparing sub- Grade Completed 4 GSB In progress 5 900 mm Dia. Pipe culvert In progress

Progress Update : 2021-03-08
On going
NA
eetmld
25.17230391537764,93.7118213081093
25.165513,93.7059129
0.96107791993383
Approved
2021-11-02 10:16:20
pwdse2ce
0
SL.No. Item Physical Progress 1 E/ W in hill cutting Completed 2 Kutcha Drain Completed 3 Preparing sub- Grade Completed 4 GSB In progress 5 900 mm Dia. Pipe culvert In progress

Progress Update : 2021-03-08
On going
NA
eetmld
25.17230391537764,93.7118213081093
25.1654972,93.7065472
0.92438918741125
Approved
2021-11-02 10:15:57
pwdse2ce
0
SL.No. Item Physical Progress 1 E/ W in hill cutting Completed 2 Kutcha Drain Completed 3 Preparing sub- Grade Completed 4 GSB In progress 5 900 mm Dia. Pipe culvert In progress