Progress
 
 
Project Details
DAR-2017-000093
FOR/PLTN/CAMPA/UKHRUL/LAMLAI CHINGPHEI PLOT-1
CA MIXED PLANTATION 130 HA AT LAMLAI CHINGPHEI PLOT-1
13/05/2015
FOREST
Ukhrul
23.01
23.01
Completed
Nil
24.96542564315907,94.15777015686058
CA MIXED PLANTATION 130 HA AT LAMLAI CHINGPHEI PLOT-1
Progress Update : 04/12/2017
Completed
Nil
rfoukhrul
24.96542564315907,94.15777015686058
24.968285,94.1506567
0.78435481971754
23.01
Part of Mixed plantation (NPV) over 130 ha. at Lamlai Chingphei Plot-I created during the year 2015-16 under CAMPA for diversion of forest land for Construction of Thoubal Multipurpose Project. The main species planted are pine ( Pinus Kesia) and Tolhao (Terminalia myriocarpa).

Progress Update : 04/12/2017
Completed
Nil
rfoukhrul
24.96542564315907,94.15777015686058
24.9657783,94.1573767
0.05577210716573
23.01
Part of Mixed Plantation (NPV) over 130 ha. at Lamlai Chingphei Plot-I created during the year 2015-16 under CAMPA for diversion of forest land for Construction of Thoubal Multipurpose Project. The main species seen / shown above is Tolhao (Terminalia myriocarpa).

Progress Update : 04/12/2017
Completed
Nil
rfoukhrul
24.96542564315907,94.15777015686058
24.9635767,94.1582183
0.21048774054088
23.01
Part of Mixed Plantation (NPV) over 130 ha. at Lamlai Chingphei Plot-I created during the year 2015-16 under CAMPA for diversion of forest land for Construction of Thoubal Multipurpose Project. The main species seen / shown above is Pine (Pinus kesia- Colser view)).