Progress
 
 
Project Details
DAR-2021-000797
EE/BPR/Impvt. rd of Mayai leikai RR drain
Improvement of road of Mayai leikai, Bishnupur ward no.10 i/c RR drain
27/03/2020
PWD
Bishnupur
87.00
51
State Plan
Completed
Phase 1
24.643164909018388,93.76462458971862
GSB, WBM Grade-III, 2 cm thick PC, E/W, C/C, Rubble Masonry, 40 mm cement concrete flooring, 12 mm cement plaster
Progress Update : 19/09/2022
Completed
Phase 1
lalit
24.643164909018388,93.76462458971862
24.6522088,93.7687472
1.0884769417107
51
Gsb wbm pc rr masonry drain etc

Progress Update : 19/09/2022
Completed
Phase 1
lalit
24.643164909018388,93.76462458971862
24.6514677,93.7687472
1.0128412569733
51
Gsb wbm pc rr masonry drain etc

Progress Update : 09/03/2021
Ongoing
Phase1
lalit
24.643164909018388,93.76462458971862
24.6481306,93.7669062
0.59834651973124
0
Shg wbm pc cc drain

Progress Update : 09/03/2021
Ongoing
Phase1
lalit
24.643164909018388,93.76462458971862
24.6483114,93.7676246
0.64759094863795
0
Shg wbm pc cc drain