Progress
 
 
Project Details
DAR-2021-000761
UKL/Lamlang Gate/71
Impvt. of IVR from Phadang to Lamlang Gate, Ukhrul.
2020-03-18
PWD
Ukhrul
100.00
86
State Plan
Completed formation widening
1
25.11109075,94.279786
Earth Work, Shingling & Culvert
Progress Update : 2021-06-21
Completed formation widening
1
eeukld
25.11109075,94.279786
25.111090752282,94.279786331598
0
Approved
2023-02-27 09:23:41
pwdse2ce
86
Earthwork, Kutcha drain

Progress Update : 2021-06-21
Completed Formation widening
1
eeukld
25.11109075,94.279786
25.111090752282,94.279786331598
0
Approved
86
Earthwork, Kutcha drain

Progress Update : 2021-06-21
Completed kutcha drain
1
eeukld
25.11109075,94.279786
25.111090752282,94.279786331598
0
Approved
86
Earthwork, Kutcha drain

Progress Update : 2021-06-21
Completed kutcha drain
1
eeukld
25.11109075,94.279786
25.111090752282,94.279786331598
0
Approved
2022-09-21 05:36:59
pwdse2ce
87.307
Earthwork, Kutcha drain

Progress Update : 2021-06-21
Completed Hill cutting
1
eeukld
25.11109075,94.279786
25.111090752282,94.279786331598
0
Approved
2023-02-27 09:25:30
pwdse2ce
86
Earthwork, Kutcha drain

Progress Update : 2021-06-21
Completed formation widening
1
eeukld
25.11109075,94.279786
25.096667272523,94.359653267971
8.1999237923274
Approved
2022-09-21 05:41:12
pwdse2ce
87.307
Earthwork, Kutcha drain

Foundation & Inauguration
-
-
-

-
-
-