Progress
 
 
Project Details
DAR-2017-000081
FOR/CONST/TML/MP
Construction of multipurpose hall at langkhong
29/03/2016
FOREST
Tamenglong
18.71
18.71
Demoimp
CSS / CPS
In progress
In progress
24.859007361136335,93.59025764465355
Construction of multipurpose hall under entry point activities undertaken under "In -Situ Resource Augmentation of Medicinal Plants" of National Medicinal Plants Board, Ministry of AYUSH, Govt. of India in Western Forest Division, Tamenglong at langkhong
Progress Update : 30/11/2017
In progress
In progress
rfotamenglong
24.859007361136335,93.59025764465355
24.8610537,93.6064265
1.6470110439957
18.71
Construction of multipurpose hall at langkhong under EPA undertaken under " in-situ resource augmentation of medicinal plants" of NMPB,Ministry of AYUSH, Govt. of India in Western forest Division Tamenglong at Langkhong

Progress Update : 30/11/2017
In progress
In progress
rfotamenglong
24.859007361136335,93.59025764465355
24.8592617,93.590095
0.03269560997696
18.71
Construction of multipurpose hall at langkhong under EPA undertaken under " in-situ resource augmentation of medicinal plants" of NMPB,Ministry of AYUSH, Govt. of India in Western forest Division Tamenglong at Langkhong

Progress Update : 30/11/2017
In progress
In progress
rfotamenglong
24.859007361136335,93.59025764465355
24.8610537,93.6064265
1.6470110439957
18.71
Construction of multipurpose hall at langkhong under EPA undertaken under " in-situ resource augmentation of medicinal plants" of NMPB,Ministry of AYUSH, Govt. of India in Western forest Division Tamenglong at Langkhong