DAR-2021-000695
EE/CDL/Chiiphur Lok-CP Road
Impvt. of road from Chiiphur Lok to Chandel-Pallel Road via Liwa Sarei Village
18/03/2020
PWD
Chandel
150.00
121
State Plan
Completed e/c Punch list items
2019-20
24.3285,94.01749
SH: Hill cutting, RCC slab culverts
Progress Update : 04/02/2023
Completed e/c Punch list items
2019-20
daniel
24.3285,94.01749
24.3283366,94.017449
0.018637153429489
121
Completed - 6 Mtr Span RCC SLAB Culvert without Parapet

Progress Update : 04/02/2023
Completed e/c Punch list items
2019-20
daniel
24.3285,94.01749
24.3283366,94.017449
0.018637153429489
121
Completed - Hill cutting

Progress Update : 04/02/2023
Completed w/o Rails
3
daniel
24.3285,94.01749
24.3288008,94.0074587
1.0168778695435
121
Completed - 6 m span RCC Slab Culvert without Hand Rails

Progress Update : 26/02/2022
Completed e/c Punch list items
2
daniel
24.3285,94.01749
24.3284542,94.0174977
0.005150812320834
121
Completed - Hill cutting in formation widening

Progress Update : 26/02/2022
Ongoing
2
daniel
24.3285,94.01749
24.3284542,94.0174977
0.005150812320834
121
Completion stage - 6 Mt span RCC culvert

Progress Update : 26/02/2022
Ongoing
2
daniel
24.3285,94.01749
24.3301916,94.010968
0.68702512902841
121
Completion stage - 6 Mt span RCC culvert

Progress Update : 10/10/2021
Ongoing
Nil
daniel
24.3285,94.01749
24.3281903,94.017208
0.044744912805988
121
SH:- Hill cutting & RCC Culvert

Progress Update : 24/09/2021
In progress
1
daniel
24.3285,94.01749
24.3298722,94.0180395
0.16241421785143
121
SH:- Hill Cutting & RCC Culverts

Progress Update : 22/09/2021
In progress
1
daniel
24.3285,94.01749
24.3325639,94.0191581
0.48243360165923
121
Hill cutting in progress

Progress Update : 22/09/2021
Completed e/c Punch list items
1
daniel
24.3285,94.01749
24.3325639,94.0191581
0.48243360165923
121
SH: Hill cutting & RCC Culvert