Progress
 
 
Project Details
DAR-2021-000689
IED/side berm-Arapti-Langdum(4.5-7)/614
M/o side berm at Arapti to Langdum (Ch 4.50 Km to 7.00 Km)
08/03/2019
PWD
Imphal-East
19.82
0.00
State Plan
completed
Final
24.706785917642947,93.96583062287903
Progress Update : 01/05/2021
completed
Final
sanasam
24.706785917642947,93.96583062287903
24.7089388,93.9560387
1.0176396328707
0
Side berm