Progress
 
 
Project Details
DAR-2021-000682
ND/Culvert/Khoupum/10
Construction of 1 No. 4 m span and 1 No. 1 m span RCC culvert between Khoupum PHC and Gaidimjang.
21/03/2020
PWD
Noney
50.00
26
State Plan
100%
Final phase
24.68493676673672,93.51850622439767
Culvert
Progress Update : 06/10/2022
100%
Final phase
7085631665
24.68493676673672,93.51850622439767
24.6830583,93.5194581
0.22994172817183
26
Completed and opened to public : 1m span culvert

Progress Update : 06/10/2022
100%
Final phase
7085631665
24.68493676673672,93.51850622439767
24.6830583,93.5194581
0.22994172817183
26
Completed and opened to public : 4m span RCC slab culvert work, Wing wall

Progress Update : 06/10/2022
100%
Final phase
7085631665
24.68493676673672,93.51850622439767
24.6830583,93.5194581
0.22994172817183
26
4m span RCC slab culvert work, Wing wall completed.

Progress Update : 06/10/2022
100%
Final phase
7085631665
24.68493676673672,93.51850622439767
24.6830583,93.5194581
0.22994172817183
26
Completed and opened to traffic : 4m span RCC slab culvert work,

Progress Update : 07/07/2021
100%
2nd & final phase
7085631665
24.68493676673672,93.51850622439767
24.6848721,93.5185701
0.0096615048532885
0
Sl. No. Sub-head/Item Financial Break-up Physical Progress 1. 4m span RCC Slab culvert 48.37% 100% 2. 1m span RCC Slab culvert 20.24% 100% 3. Retaining wall 31.37% 100%

Progress Update : 07/07/2021
100%
2nd & final phase
7085631665
24.68493676673672,93.51850622439767
24.6851222,93.51868
0.027080228453956
0
Sl. No. Sub-head/Item Financial Break-up Physical Progress 1. 4m span RCC Slab culvert 48.37% 100% 2. 1m span RCC Slab culvert 20.24% 100% 3. Retaining wall 31.37% 100%

Progress Update : 07/07/2021
100%
2nd & final phase
7085631665
24.68493676673672,93.51850622439767
24.6849941,93.5184235
0.010511622824514
0
Sl. No. Sub-head/Item Financial Break-up Physical Progress 1. 4m span RCC Slab culvert 48.37% 100% 2. 1m span RCC Slab culvert 20.24% 100% 3. Retaining wall 31.37% 100%

Progress Update : 07/07/2021
100%
2nd & final phase
7085631665
24.68493676673672,93.51850622439767
24.684943,93.5184972
0.001147052381498
0
Sl. No. Sub-head/Item Financial Break-up Physical Progress 1. 4m span RCC Slab culvert 48.37% 100% 2. 1m span RCC Slab culvert 20.24% 100% 3. Retaining wall 31.37% 100%

Progress Update : 27/02/2021
70%
1st Phase
7085631665
24.68493676673672,93.51850622439767
24.684934,93.5185589
0.0053305105644099
0
Culverts works :- earth work in foundation, C.C. 1:4:8, C.C. 1:3:6, steel work for cap & slab.

Progress Update : 27/02/2021
48%
1st Phase
7085631665
24.68493676673672,93.51850622439767
24.6850251,93.5184975
0.0098613794324024
0
Culverts works :- earth work in foundation, C.C. 1:4:8, C.C. 1:3:6, steel work for cap & slab.

Progress Update : 27/02/2021
48%
1st Phase
7085631665
24.68493676673672,93.51850622439767
24.6850251,93.5184975
0.0098613794324024
0
Culverts works :- earth work in foundation, C.C. 1:4:8, C.C. 1:3:6, steel work for cap & slab.

Progress Update : 27/02/2021
48%
1st Phase
7085631665
24.68493676673672,93.51850622439767
24.6849241,93.5185807
0.007655326181436
0
Culverts works :- earth work in foundation, C.C. 1:4:8, C.C. 1:3:6, steel work for cap & slab.