Progress
 
 
Project Details
DAR-2021-000666
SPT/Elite School-Cemetry/67
Construction of road from Elite Christian English School to Village Cemetery at Thingba khunou village 2 km
07/03/2020
PWD
Senapati
57.60
50
State Plan
copmpleted
Third phase
25.317693426447207,94.16238355636611
Earth Work, Shingling & Drain.
Progress Update : 22/09/2022
copmpleted
Third phase
eesptd
25.317693426447207,94.16238355636611
25.3336314,94.1582548
1.8200698621145
50
Proper Rolling and compaction of GSB required

Progress Update : 22/09/2022
copmpleted
Third phase
eesptd
25.317693426447207,94.16238355636611
25.3336314,94.1582548
1.8200698621145
15
hill cuuting,singling,drain

Progress Update : 27/11/2021
In progress
Phase-I
pashel
25.317693426447207,94.16238355636611
25.3285657,94.1558609
1.375194822792
0
GSB, PCC drain

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3280143,94.1608144
1.1583597053151
15
DO THIS AGAIN WITH 600 mm FILL Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50% Rain cuts to be filled-up to avoid further damage

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3280143,94.1608144
1.1583597053151
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3280143,94.1608144
1.1583597053151
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3280143,94.1608144
1.1583597053151
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3280143,94.1608144
1.1583597053151
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3280143,94.1608144
1.1583597053151
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3379135,94.1505766
2.542191673082
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3850817,94.0945124
10.131787881851
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3850817,94.0945124
10.131787881851
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3850817,94.0945124
10.131787881851
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3850817,94.0945124
10.131787881851
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3850817,94.0945124
10.131787881851
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 05/07/2021
64%
II
eesptd
25.317693426447207,94.16238355636611
25.3379135,94.1505766
2.542191673082
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 11/03/2021
60%
First
eesptd
25.317693426447207,94.16238355636611
25.3314479,94.1599268
1.5491580252465
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 11/03/2021
60%
First
eesptd
25.317693426447207,94.16238355636611
25.3314479,94.1599268
1.5491580252465
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 11/03/2021
60%
First
eesptd
25.317693426447207,94.16238355636611
25.3314479,94.1599268
1.5491580252465
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 11/03/2021
60%
First
eesptd
25.317693426447207,94.16238355636611
25.3314479,94.1599268
1.5491580252465
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 11/03/2021
60%
First
eesptd
25.317693426447207,94.16238355636611
25.3314479,94.1599268
1.5491580252465
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 11/03/2021
60%
First
eesptd
25.317693426447207,94.16238355636611
25.3314479,94.1599268
1.5491580252465
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%

Progress Update : 11/03/2021
60%
First
eesptd
25.317693426447207,94.16238355636611
25.2716333,94.0267984
14.560636882752
0
Physical progress of the work Financial break-up Physical progress 1) E/W in hill cutting 13.75% 100% 2) E/W in line drains 1.52% 100% 3) P/L GSB 34.89% 60% 4) PCC Drain 36.03% 60% 5) Pipe culvert 900.00 mm dia (4 Nos.)13.75% 50%