Progress
 
 
Project Details
DAR-2021-000504
JJM/KANGPOKPI/JANGNOM II/58
Water Supply Scheme at Jangnom
15/07/2020
PHED
Kangpokpi
25.00
0.00
CSS / CPS
40%
Phase I
25.0855217,93.87336739999999
Construction of Settling Tank and Distribution Tank
Progress Update : 22/03/2021
40%
Phase I
sudhir
25.0855217,93.87336739999999
25.0853295,93.91821
4.5157813642351
0
Settling Tank

Progress Update : 21/02/2021
Initial
Phase I
sudhir
25.0855217,93.87336739999999
25.0834625,93.9188469
4.585622333626
0
Distribution Tank