Progress
 
 
Project Details
DAR-2021-000470
MSPDCL-SAUBHAGYA-073
Supply & Erection of all equipments and materials required for Implementation of SAUBHAGYA Scheme and Additional infra for SAUBHAGYA under DDUGJY
2018-07-30
POWER (MSPDCL)
Imphal-East
901.71
490.62
MOP & State Share
Completed
1
24.922752,94.010417
Supply & Erection of all equipments and materials required for Implementation of SAUBHAGYA Scheme and Additional infra for SAUBHAGYA under DDUGJY of Imphal-East District on turn-key basis
Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9523422,94.0202211
3.4354031130985
Approved
2021-02-23 10:26:32
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9490965,94.0170302
3.0041631258002
Approved
2021-02-23 10:38:45
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9477724,94.0193473
2.9240866234307
Approved
2021-02-23 11:11:16
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9482152,94.0190859
2.9630862708978
Approved
2021-02-24 03:16:32
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9487341,94.0193749
3.026829234547
Approved
2021-02-24 03:16:46
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9491581,94.0196913
3.0813878741055
Approved
2021-02-24 03:17:00
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9496184,94.0198853
3.1360916286245
Approved
2021-02-24 03:17:18
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9502801,94.0190767
3.1829296408073
Approved
2021-02-24 03:17:34
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.950049,94.0194432
3.1686420288708
Approved
2021-02-24 03:17:49
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.949888,94.0197884
3.1617251892656
Approved
2021-02-25 06:37:35
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9497904,94.0198226
3.1524063603135
Approved
2021-02-25 06:37:22
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9498302,94.0199454
3.1603685790536
Approved
2021-02-25 06:37:08
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9498044,94.019993
3.1590992394998
Approved
2021-02-25 06:36:18
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9497399,94.0199454
3.1508048779161
Approved
2021-02-25 06:36:05
CORPORATEAP2
0
Photos

Progress Update : 2021-02-22
Completed
1
Chetan
24.922752,94.010417
24.9498163,94.0199703
3.1596606463723
Approved
2021-02-25 06:35:52
CORPORATEAP2
0
Photos

Foundation & Inauguration
-
-
-

-
-
-