Progress
 
 
Project Details
DAR-2021-000423
SPT/NH-102 (A) to Saranamei Village/61
Improvement of NH-102 (A) to Saranamei Village - 4.00 km.
07/03/2020
PWD
Senapati
120.00
97
State Plan
100%
Phase I
25.475031321042888,94.20549738407149
Shingling, WBM, PC & Culvert
Progress Update : 24/02/2021
100%
Phase I
eesptd
25.475031321042888,94.20549738407149
25.46052793,94.2033946
1.6263826257239
97
1) Earthwork - 1% 2) GSB - 21% 3) WBM - 46% 4) PC - 26% 5) RCC pipe culvert - 5%

Progress Update : 24/02/2021
100%
Phase I
eesptd
25.475031321042888,94.20549738407149
25.46052793,94.2033946
1.6263826257239
97
1) Earthwork - 1% 2) GSB - 21% 3) WBM - 46% 4) PC - 26% 5) RCC pipe culvert - 5%

Progress Update : 24/02/2021
100%
Phase I
eesptd
25.475031321042888,94.20549738407149
25.46885397,94.2090699
0.77483997572328
0
1) Earthwork - 1% 2) GSB - 21% 3) WBM - 46% 4) PC - 26% 5) RCC pipe culvert - 5%

Progress Update : 24/02/2021
100%
Phase I
eesptd
25.475031321042888,94.20549738407149
25.47122003,94.2063443
0.43221904288076
0
1) Earthwork - 1% 2) GSB - 21% 3) WBM - 46% 4) PC - 26% 5) RCC pipe culvert - 5%

Progress Update : 24/02/2021
100%
Phase I
eesptd
25.475031321042888,94.20549738407149
25.47534641,94.20555963
0.035587377213432
0
1) Earthwork - 1% 2) GSB - 21% 3) WBM - 46% 4) PC - 26% 5) RCC pipe culvert - 5%