Progress
 
 
Project Details
DAR-2021-000419
SPT/Approach road Mao I.B/58
Improvement of approach road of Mao I.B
2020-03-07
PWD
Senapati
30.00
22
State Plan
Completed
Phase 1
25.512526086637678,94.13667726516738
Shingling, WBM, PC & PCC Drain
Progress Update : 2022-10-07
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51288538,94.13596357
0.082006360905173
Approved
2022-10-12 11:11:00
pwdse2ce
22
Completed PC surface

Progress Update : 2022-10-07
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51213006,94.13607994
0.07437633419706
Approved
2022-10-12 11:11:40
pwdse2ce
22
Completed PC surface

Progress Update : 2022-10-07
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51213006,94.13607994
0.07437633419706
Approved
22
PC & SC completed

Progress Update : 2021-04-26
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5123921,94.1358634
0.083017181679386
Approved
2022-10-12 11:13:52
pwdse2ce
22
Completed BT surface

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5145909,94.136503
0.23025074429135
Approved
2021-03-10 11:12:34
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5083101,94.136503
0.4690998376917
Approved
2021-03-10 11:13:06
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5108963,94.136503
0.18205709475895
Approved
2021-03-10 11:13:34
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5105358,94.1361832
0.22678480645147
Approved
2021-03-10 11:14:10
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5098149,94.1355436
0.3222069264538
Approved
2021-03-10 11:14:46
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5097969,94.1361832
0.30748053368904
Approved
2021-03-10 11:11:59
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51250839,94.13647099
0.02079243066892
Approved
2021-03-10 11:10:12
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5097969,94.1361832
0.30748053368904
Approved
2021-03-10 11:09:06
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 2021-03-09
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5097969,94.1361832
0.30748053368904
Approved
2021-03-10 11:08:27
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Foundation & Inauguration
-
-
-

-
-
-