Progress
 
 
Project Details
DAR-2021-000419
SPT/Approach road Mao I.B/58
Improvement of approach road of Mao I.B
07/03/2020
PWD
Senapati
30.00
22
State Plan
Completed
Phase 1
25.512526086637678,94.13667726516738
Shingling, WBM, PC & PCC Drain
Progress Update : 07/10/2022
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51288538,94.13596357
0.082006360905173
22
Completed PC surface

Progress Update : 07/10/2022
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51213006,94.13607994
0.07437633419706
22
Completed PC surface

Progress Update : 07/10/2022
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51213006,94.13607994
0.07437633419706
22
PC & SC completed

Progress Update : 26/04/2021
Completed
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5123921,94.1358634
0.083017181679386
22
Completed BT surface

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5145909,94.136503
0.23025074429135
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5083101,94.136503
0.4690998376917
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5108963,94.136503
0.18205709475895
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5105358,94.1361832
0.22678480645147
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5098149,94.1355436
0.3222069264538
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5097969,94.1361832
0.30748053368904
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.51250839,94.13647099
0.02079243066892
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5097969,94.1361832
0.30748053368904
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%

Progress Update : 09/03/2021
80%
Phase 1
eesptd
25.512526086637678,94.13667726516738
25.5097969,94.1361832
0.30748053368904
0
Physical progress of the work Financial break-up Physical progress 1) PCC Drain 55.72% 100% 2) GSB 13.28% 100% 3) WBM 14.45% 100% 4) PC 16.55% 0%