DAR-2021-000417
EE/HS/Impvt of Mayang Imphal Anilongbi Yumn
Impvt. of Mayang Imphal Anilongbi Yumnam Leirak connecting Sanoujam Leirak (1.1km) Tongbram Leirak (660m), Ningthoujam Leirak (1.5m) Khoirom Leirak
07/03/2020
PWD
Imphal-West
120.00
78
State Plan
100pc
Phase 1
24.62165335845451,93.88198157746275
GSB, WBM, PC and Cross Drainage works
Progress Update : 18/02/2021
100pc
Phase 1
mfrahman
24.62165335845451,93.88198157746275
24.6179843,93.8877118
0.708468672081
78
GSB, WBM III, 2 CM PC, CULVERT

Progress Update : 18/02/2021
In progress
Phase 1
mfrahman
24.62165335845451,93.88198157746275
24.6185723,93.8868199
0.59711454437819
68
GSB, WBM III, 2 CM PC, CULVERT

Progress Update : 18/02/2021
In progress
Phase 1
mfrahman
24.62165335845451,93.88198157746275
24.6219622,93.880326
0.17083269632348
0
GSB, WBM III, 2CM PC, CULVERTS