Progress
 
 
Project Details
DAR-2021-000399
UKL/Nungshong/65
Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms)
2020-03-17
PWD
Ukhrul
100.00
66
State Plan
Completed
1
25.084581063270583,94.36732122519531
Culvert, Shingling & Kutcha Drain
Progress Update : 2023-03-03
Completed
1
eeukld
25.084581063270583,94.36732122519531
25.0913749,94.3659876
0.76724850581346
Approved
2023-03-07 06:47:00
pwdse2ce
66
Pipe Culvert

Progress Update : 2023-03-03
Completed
1
eeukld
25.084581063270583,94.36732122519531
25.0913749,94.3659876
0.76724850581346
Approved
2023-03-07 06:50:13
pwdse2ce
66
Pipe Culvert

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:46:42
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:45:40
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:44:58
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:44:26
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:43:32
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:42:02
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:41:28
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:40:51
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:40:15
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:39:40
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Progress Update : 2021-02-24
Ongoing
1
eeukld
25.084581063270583,94.36732122519531
25.072756741,94.374102098
1.4815111351906
Approved
2021-03-09 08:38:53
pwdse2ce
0
Sl. No. Items/Particulars Financial Break-up Physical Progress 1. GSB 90.07% 75% 2. Kutcha drain 4.19% 60% 3. 600 mm pipe culvert 2.83% 0.00% 4. 900 mm pipe culvert 2.90% 0.00%

Foundation & Inauguration
-
-
-

-
-
-