Progress
 
 
Project Details
DAR-2021-000343
JJM/KANGPOKPI/GAMNOMPHAI/29
Water Supply Scheme at Gamnomphai
15/07/2020
PHED
Kangpokpi
30.00
0.00
CSS / CPS
Initial
Phase I
24.5903186,93.6608122
Construction of Settling Tank and Distribution Tank
Progress Update : 08/02/2021
Initial
Phase I
sudhir
24.5903186,93.6608122
25.082269,93.9360474
61.34644079435
0
DistributionTank

Progress Update : 08/02/2021
Initial
Phase I
sudhir
24.5903186,93.6608122
25.0822606,93.936366
61.360169517196
0
Settling Tank