Progress
 
 
Project Details
DAR-2017-000041
MSPCLC12
Installation of 2x5 MVA 33KV S/S along with the associated 33KV line and related civil works at Wangoi under IPDS
2016-05-11
POWER (MSPCL)
Imphal-West
1249.00
914.24
IPDS/State Plan
100%
Completed
24.67037627129524,93.89935325714714
Construction of 2x5 MVA 33KV S/S along with the associated 33KV line and related civil works at Wangoi under IPDS for providing 24x7 power to area around Wangoi.
Progress Update : 2020-03-06
100%
Completed
tapan
24.67037627129524,93.89935325714714
24.6540925,93.898787
1.8114895385631
Approved
2020-03-06 12:26:10
davidkumar
0
Completed

Progress Update : 2019-02-01
75% complete
In progress
tapan
24.67037627129524,93.89935325714714
24.6562335,93.913979
2.1580016168446
Approved
2019-02-26 11:33:32
davidkumar
0
In progress

Progress Update : 2019-02-01
75% complete
In progress
tapan
24.67037627129524,93.89935325714714
24.6565397,93.9160983
2.286891560798
Approved
2019-02-26 11:33:51
davidkumar
0
In progress

Progress Update : 2019-02-01
75% complete
In progress
tapan
24.67037627129524,93.89935325714714
24.65619,93.916
2.3059748217544
Approved
2019-02-01 11:39:11
davidkumar
189.51
In progress

Progress Update : 2019-02-01
75% complete
In progress
tapan
24.67037627129524,93.89935325714714
24.6562158,93.9160582
2.3083103367757
Approved
2019-02-01 11:40:30
davidkumar
0
In progress

Progress Update : 2019-02-01
75% complete
In progress
tapan
24.67037627129524,93.89935325714714
24.6561567,93.9162217
2.3248830986042
Approved
2019-02-01 11:39:35
davidkumar
0
In progress

Foundation & Inauguration
-
-
-

-
-
-