Progress
 
 
Project Details
DAR-2017-000040
MSPCLB7
Installation of 2x12.5 MVA, 132/33 kV Sub-Station along with associated 132 kV LILO line & related works at Tipaimukh in Manipur
18/12/2015
POWER (MSPCL)
Pherzawl
5139.00
3523.89
Demoimp
State Plan
100%
Completed
24.217750, 93.033611
Construction of 2x12.5 MVA, 132/33 kV Sub-Station along with associated 132 kV LILO line & related works at Tipaimukh in Manipur for providing good quality 24 X 7 power to area around Pherzawl District head quarter.
Progress Update : 03/12/2018
100%
Completed
tapan
24.217750, 93.033611
24.8002178,93.9354293
111.8866305918
0
132/33kV Tipaimukh sub station , control room

Progress Update : 03/12/2018
100%
I
tapan
24.217750, 93.033611
24.8005604,93.9357288
111.93328754882
0
132/33kV Tipaimukh sub station , 33 kV switchyard