Progress
 
 
Project Details
DAR-2021-000160
TBL/Darpan/Plan/110
Construction of Siphai Leikai IVR.
13/03/2020
PWD
Thoubal
50.00
32
State Plan
80%
2nd phase
24.6673704,94.0362923
Shingling,WBM,PC wIth CC drain
Progress Update : 20/08/2024
80%
2nd phase
leisem1
24.6673704,94.0362923
24.666725,94.0379583
0.18299591843618
32
gsb, WBM, pc and pucca drain

Progress Update : 20/03/2023
75pc
2nd phase
leisem1
24.6673704,94.0362923
24.6663865,94.0367442
0.11854628680306
22
Construction of Siphai Leikai IVR