Progress
 
 
Project Details
DAR-2021-000022
SPT/Thiva/51
Improvement of road from Khongdei Shimpung to Thiva via Thiva Songdo - 6 km.
16/03/2020
PWD
Senapati
80.00
60
State Plan
Completed
Phase-1
25.310994893049568,94.26802273432696
Shingling, WBM & Culvert
Progress Update : 05/03/2021
Completed
Phase-1
eesptd
25.310994893049568,94.26802273432696
25.2446706,94.3045475
8.2383323879539
60
Financial Break-up 1)EW - 1.35% (physical - 100%) 2) GSB - 45.79% (physical - 100%) ii) WBM - 43.97% (physical - 100%) iii) RCC - 8.87% (physical - 100%)

Progress Update : 05/03/2021
Completed
Phase-1
eesptd
25.310994893049568,94.26802273432696
25.2841792,94.3972725
13.330754093158
0
Financial Break-up 1)EW - 1.35% (physical - 100%) 2) GSB - 45.79% (physical - 100%) ii) WBM - 43.97% (physical - 100%) iii) RCC - 8.87% (physical - 100%)

Progress Update : 05/03/2021
Completed
Phase-1
eesptd
25.310994893049568,94.26802273432696
25.2841792,94.3972725
13.330754093158
0
Financial Break-up 1)EW - 1.35% (physical - 100%) 2) GSB - 45.79% (physical - 100%) ii) WBM - 43.97% (physical - 100%) iii) RCC - 8.87% (physical - 100%)

Progress Update : 05/03/2021
Completed
Phase-1
eesptd
25.310994893049568,94.26802273432696
25.2841792,94.3972725
13.330754093158
0
Financial Break-up 1)EW - 1.35% (physical - 100%) 2) GSB - 45.79% (physical - 100%) ii) WBM - 43.97% (physical - 100%) iii) RCC - 8.87% (physical - 100%)