Progress
 
 
Project Details
DAR-2021-000017
EE/CDL/Impvt of Unapal road 2.50km
Impvt. of Unapal road
2020-03-16
PWD
Chandel
80.00
67
State Plan
100%
2
24.453232,94.0118
Sand Gravel, WBM and PC 2.50km
Progress Update : 2021-10-17
100%
2
daniel
24.453232,94.0118
24.4546423,94.0173782
0.58597055211555
Approved
2023-02-03 10:55:14
pwdse2ce
67
Completed - Premix Carpet

Progress Update : 2021-10-17
100%
2
daniel
24.453232,94.0118
24.4546423,94.0173782
0.58597055211555
Approved
67
Completed - Premix Carpet

Progress Update : 2021-01-25
100%
first
daniel
24.453232,94.0118
24.451971666667,94.008905
0.32480690614123
Approved
67
WBM - In progress

Progress Update : 2021-01-25
100%
first
daniel
24.453232,94.0118
24.45227,94.00869
0.3324595081699
Approved
67
Ongoing - WBM in progress

Foundation & Inauguration
-
-
-

-
-
-