Progress
 
 
Project Details
DAR-2020-001713
IED/Singling-side berm-Yaiskul AC/528
Singling of road and Constn. of side berm in and around Yaiskul A/C
23/03/2020
PWD
Imphal-East
30.00
0.00
State Plan
In progress
NA
24.793932885706628,93.9462940692903
Progress Update : 04/01/2021
In progress
NA
shibadatta
24.793932885706628,93.9462940692903
24.7919928,93.9539965
0.80686291133222
0
Shingling