Progress
 
 
Project Details
DAR-2020-001710
BRD/Bridge-Mayang Langjing Kuthabi/34
Construction of RCC Bridge over Nambul River at Mayang Langjing Kuthabi Lampak
2020-03-17
PWD
Imphal-West
284.23
260
State Plan
Completed
---
24.860462698581866,93.86107760667815
Progress Update : 2023-01-04
Completed
---
so1brd2
24.860462698581866,93.86107760667815
24.8602814,93.8618616
0.081622599215466
Approved
2024-07-31 10:30:59
se1pwd
260
Constn of RCC Bridge, PW Approach road - completed

Progress Update : 2021-11-24
Ongoing
2
so1brd
24.860462698581866,93.86107760667815
24.8603933,93.8618582
0.079128166423875
Approved
2022-09-06 09:15:22
se1pwd
180
Under State plan. Main Bridge completed, approach on progress

Progress Update : 2021-11-24
Ongoing
Final
so1brd
24.860462698581866,93.86107760667815
24.8645353,93.8536012
0.87974640072605
Approved
2021-12-01 10:17:59
se1pwd
180
Under State plan. Main Bridge completed, approach on progress

Foundation & Inauguration
-
-
-

-
-
-