Progress
 
 
Project Details
DAR-2020-001322
IED/Laishram Leirak/498
Improvement of road at Laishram Leirak including R/W and drainage system
2020-03-23
PWD
Imphal-East
52.23
44.5
State Plan
Completed
1
24.757518835241946,93.93668607623519
Progress Update : 2020-12-05
Completed
1
mak
24.757518835241946,93.93668607623519
24.7577946,93.9353914
0.1342711206373
Approved
44.5
Road ,Drain, Rw

Progress Update : 2020-12-05
Completed
---
mak
24.757518835241946,93.93668607623519
24.7577946,93.9353914
0.1342711206373
Approved
2026-01-16 07:40:04
se1pwd
44.5
Impvt of Road

Foundation & Inauguration
-
-
-

-
-
-