Progress
 
 
Project Details
DAR-2020-001179
TPL-CSC-SAMUKOM
CONSTRUCTION OF COMMUNITY SANITARY COMPLEX ATSAMUKOM
20/11/2019
PHED
Tengnoupal
200000.00
120000
Completed
Phase 1
24.466784832920798,94.19459152221694
CSC AT SAMUKOM
Progress Update : 01/12/2020
Completed
Phase 1
tengnoupal
24.466784832920798,94.19459152221694
24.47264365,94.19243665
0.68697275006609
120000
CSC AT SAMUKOM

Progress Update : 01/12/2020
Completed
Phase 1
tengnoupal
24.466784832920798,94.19459152221694
24.47264365,94.19243665
0.68697275006609
120000
CSC AT SAMUKOM