Progress
 
 
Project Details
DAR-2020-001132
TPL-CSC- T.YANGNOM
CONSTRUCTION OF COMMUNITY SANITARY COMPLEX AT T.YANGNOM
20/11/2019
PHED
Tengnoupal
200000.00
120000
Completed
Phase 1
24.18280081236089,94.19244575500502
CSC AT T.YANGNOM
Progress Update : 02/12/2020
Completed
Phase 1
tengnoupal
24.18280081236089,94.19244575500502
24.2475288,94.2967428
12.792865267241
120000
CSC AT YANGNOM

Progress Update : 02/12/2020
Completed
Phase 1
tengnoupal
24.18280081236089,94.19244575500502
24.2475288,94.2967428
12.792865267241
120000
CSC AT YANGNOM