Progress
 
 
Project Details
DAR-2020-001018
TPL-CSC-LANGOL KHULLEN
Construction of Community Sanitary Complex at LANGOL KHULLEN
20/11/2019
PHED
Tengnoupal
200000.00
120000
Completed
Phase 1
24.50037333632384,94.07348442077651
CSC AT LANGOL KHULLEN
Progress Update : 27/11/2020
Completed
Phase 1
tengnoupal
24.50037333632384,94.07348442077651
24.5016719,94.0729623
0.15374722748342
120000
CSC AT LANGOL KHULLEN