Progress
 
 
Project Details
DAR-2020-000893
IED/Aribam Leikai-Yaiskul AC/465
Impvt. of road and drainage sysytem of Aribam Leikai under Yaiskul A/C
2020-03-07
PWD
Imphal-East
45.00
0.00
State Plan
Completed
Na
24.787903758280738,93.94505488872542
Progress Update : 2020-11-29
Completed
Na
shibadatta
24.787903758280738,93.94505488872542
24.7867824,93.9445809
0.13354881355677
Approved
0
Road

Foundation & Inauguration
-
-
-

-
-
-