Progress
 
 
Project Details
DAR-2020-000867
7/1/2020- PHE(10B)(CharoiChagotlong-I. JJM)
Aug. of Water Supply scheme at Charoichagotlong-I
15/07/2020
PHED
Noney
50.00
0.00
Central Sector
24.7613715,93.5776061
1. Construction of Intake Arrangement. 2. Construction of Distribution Tank - 3000 Ltr. Capacity. 3. Construction of Settling Tank - 15,000 Ltr. Capacity. 4. Construction of Zonal Reservoir - 20,000 Ltr. capacity. 5. Mechanical Transportation of G.I. Pipe. 6. Laying and Fixing of G.I. Pipe