Progress
 
 
Project Details
DAR-2020-000743
JJM Senapati/Laii Shirafii
Augmentation of Laii Shirafii W/S scheme
2020-07-15
PHED
Senapati
120.00
22.53
Central Sector
In progress
II
25.536011117005575,94.43010947895966
Progress Update : 2022-05-19
In progress
II
Ashuli
25.536011117005575,94.43010947895966
25.53559976,94.43046255
0.057851615924805
Approved
2022-05-19 09:32:00
eesptphed
0
Distribution tank 5

Progress Update : 2022-05-19
In progress
II
Ashuli
25.536011117005575,94.43010947895966
25.535382,94.4248004
0.5372241093736
Approved
2022-05-19 09:31:53
eesptphed
0
Zonal reservoir

Progress Update : 2020-11-24
In progress
I
Ashuli
25.536011117005575,94.43010947895966
25.53610661,94.42978151
0.034575122234099
Approved
2020-12-11 08:50:42
eesptphed
0
Distribution tank

Progress Update : 2020-11-24
In progress
I
Ashuli
25.536011117005575,94.43010947895966
25.520821,94.4177266
2.0967330005773
Approved
2020-12-11 08:50:56
eesptphed
0
Slow sand filter

Progress Update : 2020-11-24
In progress
I
Ashuli
25.536011117005575,94.43010947895966
25.53574736,94.42982292
0.041068486716609
Approved
2020-12-11 08:51:11
eesptphed
0
Slow sand filter

Foundation & Inauguration
-
-
-

-
-
-