Project Details
DAR-2020-000573
SS/19-KakchingKhullenUPS-KAK
Strengthening of School under Samagra Shiksha for the year 2019-20 of Kakching Khullen Upper Primary School, Kakching District, Manipur.
2019-12-16
Education (S)
Kakching
37.36
29.17
Samagra Shiksha
Completed
nill
24.493438950884514,93.99350113053285
Strengthening of School under Samagra Shiksha for the year 2019-20 of Kakching Khullen Upper Primary School, Kakching District, Manipur. (SH: Construction of 2(two) ACRs) (Providing of IEI)
Progress Update : 2022-09-10
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.49347531,93.9936061
0.011364758796592
Approved
2023-04-17 09:18:49
ee2.eew-mn
0
Front View

Progress Update : 2022-09-10
Completed IEI
Front view
so7.eew
24.493438950884514,93.99350113053285
24.4926498,93.9947799
0.15633684876919
Approved
2023-12-01 07:46:00
ee2.eew-mn
0
Interior view (Providing of IEI)

Progress Update : 2022-09-10
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.4926399,93.9948871
0.16601275971929
Approved
2023-04-17 09:18:11
ee2.eew-mn
0
Interior View

Progress Update : 2022-09-10
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.49341886,93.99348434
0.0028064837979574
Approved
2023-04-17 09:17:10
ee2.eew-mn
0
Interior View

Progress Update : 2022-09-10
Completed IEI
Front view
so7.eew
24.493438950884514,93.99350113053285
24.49406422,93.99326651
0.073464794149065
Approved
2023-12-01 07:38:27
ee2.eew-mn
0
Electric Fuse

Progress Update : 2022-09-10
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.49332588,93.99358046
0.01491591079511
Approved
2023-04-17 09:15:49
ee2.eew-mn
0
Verandah View

Progress Update : 2022-09-10
Completed IEI
Front view
so7.eew
24.493438950884514,93.99350113053285
24.49335009,93.99337463
0.016169465253465
Approved
2023-12-01 07:49:08
ee2.eew-mn
0
Front view (Providing of IEI)

Progress Update : 2022-06-10
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4926245,93.9949172
0.16950200277495
Approved
2022-06-28 08:37:33
ee2.eew-mn
0
Verandah View

Progress Update : 2022-06-10
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4920146,93.9886733
0.5135306803947
Approved
2022-06-28 08:39:00
ee2.eew-mn
0
Interior View

Progress Update : 2022-06-10
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4933578,93.9946994
0.12158043689069
Approved
2022-06-28 08:39:47
ee2.eew-mn
0
Interior View

Progress Update : 2022-06-10
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4939172,93.9885725
0.501522185203
Approved
2022-06-28 08:40:47
ee2.eew-mn
0
Front view

Progress Update : 2020-10-02
Work in progress
Nill
kh1.eew-mn
24.493438950884514,93.99350113053285
24.493626,93.9937526
0.032863039075424
Approved
2020-10-29 08:30:26
ce.eew-mn
0
Back view

Progress Update : 2020-10-02
Work in progress
Nill
kh1.eew-mn
24.493438950884514,93.99350113053285
24.4925913,93.9956563
0.23756435710299
Approved
2020-10-29 08:30:11
ce.eew-mn
0
Front view

Progress Update : 2020-10-02
Work in progress
Nill
kh1.eew-mn
24.493438950884514,93.99350113053285
24.4925913,93.9956563
0.23756435710299
Approved
2020-10-29 08:29:21
ce.eew-mn
0
Front view

Foundation & Inauguration
-
-
-

-
-
-