Progress
 
 
Project Details
DAR-2020-000535
IED/Naharup Thong-Makha Pat/407
Impvt. of road from Naharup Thong to Makha Pat Eastern side - 1.5 km
2020-03-23
PWD
Imphal-East
50.00
29
State Plan
completed
phase 3
24.791751110718735,93.97689914987637
Progress Update : 2024-07-25
completed
phase 3
mstqahmed7
24.791751110718735,93.97689914987637
24.789567,93.9864781
0.99695832541154
Approved
2025-03-18 09:22:26
se1pwd
29
Road work

Progress Update : 2024-07-25
completed
phase 3
mstqahmed7
24.791751110718735,93.97689914987637
24.789567,93.9864781
0.99695832541154
Approved
2025-03-18 09:22:43
se1pwd
29
Road work

Progress Update : 2021-11-08
Completed
---
sanasam
24.791751110718735,93.97689914987637
24.8050636,93.9609714
2.1853381688501
Approved
2025-02-28 12:05:03
se1pwd
29
Impvt of road

Progress Update : 2020-09-13
Ongoing
1st
mstqahmed7
24.791751110718735,93.97689914987637
24.7964306,93.9800302
0.60877731187659
Approved
2020-11-23 09:35:30
se1pwd
0
GSB

Foundation & Inauguration
-
-
-

-
-
-