Progress
 
 
Project Details
DAR-2020-000459
MSPDCL-R&E-I-056
Erection, Installation & Commissioning of L.T. Lines at Thoubal Sub-Division of Thoubal Division under Non-Project Area.Keibung Bazar
2016-05-25
POWER (MSPDCL)
Thoubal
20.47
0.00
MH 8449
Completed
R&E-1
24.6379514,93.9448761
Erection, Installation & Commissioning of L.T. Lines at Thoubal Sub-Division of Thoubal Division under Non-Project Area.Keibung Bazar Impanelled Firm: M/S Yumnam Construction
Progress Update : 2020-11-06
Completed
R&E-1
THOUMA1
24.6379514,93.9448761
24.6264704,93.933621
1.7098803651171
Approved
2020-11-06 09:00:49
CORPORATEAP2
0
Erection, installation and commissioning of LT lines at thoubal sub division of thoubal division under non project area. Leishangthem khongmanung

Progress Update : 2020-11-06
Completed
R&E-1
THOUMA1
24.6379514,93.9448761
24.6264704,93.933621
1.7098803651171
Approved
2020-11-06 09:01:03
CORPORATEAP2
0
Erection, installation and commissioning of LT lines at thoubal sub division of thoubal division under non project area. Leishangthem khongmanung

Progress Update : 2020-11-06
Completed
R&E-1
THOUMA1
24.6379514,93.9448761
24.6371974,93.94751413
0.27948875906411
Approved
2020-11-06 09:01:20
CORPORATEAP2
0
Erection, installation and commissioning of LT lines at thoubal sub division of thoubal division under non project area. Keibung bazar

Progress Update : 2020-11-06
Completed
R&E-1
THOUMA1
24.6379514,93.9448761
24.6615648,93.9696678
3.6291227043161
Approved
2020-11-06 09:12:09
CORPORATEAP2
0
Erection, installation and commissioning of LT lines at thoubal sub division of thoubal division under non project area. Keibung bazar

Progress Update : 2020-11-06
Completed
R&E-1
THOUMA1
24.6379514,93.9448761
24.6615648,93.9696678
3.6291227043161
Approved
2020-11-06 09:12:29
CORPORATEAP2
0
Erection, installation and commissioning of LT lines at thoubal sub division of thoubal division under non project area. Keibung bazar

Foundation & Inauguration
-
-
-

-
-
-