Progress
 
 
Project Details
MSPCLC5
Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen
2014-07-02
POWER (MSPCL)
Ukhrul
1449.83
1442.99
NLCPR
100%
100%
25.124162,94.274983
i) Construction of 2x5 MVA 33 kV Sub-Station at Nungbi Khullen. ii) Stringing of 33 kV line from Hundung to Nungbi Khullen. iii) Associated civil works.
Progress Update : 2020-10-05
100%
100%
raiping
25.124162,94.274983
25.2080632,94.4588964
20.726355600195
Approved
2020-10-05 09:50:55
davidkumar
0
Xyz

Progress Update : 2020-10-05
100%
100%
raiping
25.124162,94.274983
25.2076935,94.4588964
20.707911054042
Approved
2020-10-05 09:51:12
davidkumar
0
Xyz

Progress Update : 2020-10-05
100%
100%
raiping
25.124162,94.274983
25.2076935,94.4588964
20.707911054042
Approved
2020-10-05 09:52:49
davidkumar
0
Xyz

Progress Update : 2020-01-02
100
Y
ramzik
25.124162,94.274983
25.069111,94.3441325
9.2708677646543
Approved
2020-01-10 08:52:04
davidkumar
0
Nungbi 33kv line

Progress Update : 2018-03-11
100
X
frostcosta
25.124162,94.274983
25.2165854,94.4639842
21.618261477121
Approved
2018-03-15 11:31:26
davidkumar
0
Y

Progress Update : 2018-03-11
100
X
frostcosta
25.124162,94.274983
25.2165993,94.464104
21.629602122379
Approved
2018-03-15 11:31:32
davidkumar
0
Y

Progress Update : 2018-03-11
100
X
frostcosta
25.124162,94.274983
25.2163295,94.4641174
21.61656903238
Approved
2018-03-15 11:31:39
davidkumar
0
Y

Progress Update : 2018-03-11
100
X
frostcosta
25.124162,94.274983
25.2163314,94.4641169
21.61662475546
Approved
1136.92
Y

Progress Update : 2017-11-18
85%
X
gumnomss
25.124162,94.274983
25.2165683,94.4640733
21.625248090299
Approved
0
Y

Progress Update : 2017-11-18
85%
X
gumnomss
25.124162,94.274983
25.2165417,94.4641683
21.632257913802
Approved
2017-12-20 06:48:29
davidkumar
0
Y

Progress Update : 2017-11-18
100%
completed
gumnomss
25.124162,94.274983
25.2164683,94.4641483
21.626617341312
Approved
1136.92
Y

Foundation & Inauguration
-
-
-

-
-
-