MSPCLC4
Installation of 2x2.5 MVA, 33/11 kV Sub-Station at Kasom Khullen with associated 33 kV line and related civil work
2015-03-20
POWER (MSPCL)
Ukhrul
1042.26
941.30
State Plan
100 %
Completed
24.402988,94.1628.85
i) Construction of 2x5 MVA 33 kV Sub-Station at Kasom Khullen.
ii) Stringing of 33 kV line from Thoubal to Kasom Khullen.
iii) Associated civil works