Progress
 
 
Project Details
IFCD-FCW-18
Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.
24/08/2017
Water Resources Department (WRD)
Imphal East & West
750.01
0.00
State Plan
Completed
Phase-1
24.822647573427236,93.97176432609581
The project provides dredging work, strengthening river bund by construction retaining wall with bore in Kongba, Imphal and Nambul River.
Progress Update : 13/02/2018
Completed
Phase-1
FCD-1
24.822647573427236,93.97176432609581
24.7256034,93.9480452
11.052813546086
0
Re-sectioning works of Imphal River Kiyamgei (RBB)

Progress Update : 13/02/2018
Completed
Phase-1
FCD-1
24.822647573427236,93.97176432609581
24.7386927,93.9548516
9.4897607402885
0
Re-sectioning works of Kongba River from Rd.31.05km to Rd.31.90km (LBB)

Progress Update : 13/02/2018
Completed
Phase-1
FCD-1
24.822647573427236,93.97176432609581
24.7389418,93.9547569
9.4642460126857
0
Re-sectioning works of Kongba River from Rd.31.05km to Rd.31.90km (LBB)

Progress Update : 04/12/2017
On going
1
FCD-1
24.822647573427236,93.97176432609581
24.7380243,93.9567956
9.5297952532077
0
Dredging of kongba river at Md Oja Hakim mapa (LBB)

Progress Update : 27/11/2017
Work in progress
First phase
FCD-1
24.822647573427236,93.97176432609581
24.7261493,93.9483504
10.986893300853
0
River dredging on the RBB of Imphal River at MLA Rameshor Mapa