Progress
 
 
Project Details
DAR-2020-000236
SS/19-BalaramKhulUPS-BPR
Strengthening of School under Samagra Shiksha for the year 2019-2020 Balaram Khul UPS, Bishnupur District, Manipur.
2019-12-16
Education (S)
Bishnupur
56.04
28.26
Samagra Shiksha
Completed
Nil
24.722645427399318,93.81072432943037
Strengthening of School under Samagra Shiksha for the year 2019-2020 Balaram Khul UPS, Bishnupur District, Manipur. (SH: Construction of 3(three) ACRs)
Progress Update : 2023-10-13
Completed
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7073843,93.8141758
1.7323185669867
Approved
0
Veranda IEI

Progress Update : 2023-10-13
Completed
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7226214,93.8106121
0.011645180227192
Approved
0
Room IEI

Progress Update : 2023-10-13
Completed
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7224033,93.8108198
0.028596690994351
Approved
0
Front view IEI

Progress Update : 2022-05-13
Completed
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7224746,93.8108375
0.022168307452483
Approved
2022-08-11 06:38:14
ee1.eew
0
Front view

Progress Update : 2022-05-13
Completed
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7227115,93.8109569
0.024611238165232
Approved
2022-08-11 06:39:49
ee1.eew
0
Verandah

Progress Update : 2022-05-13
Completed
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7244822,93.8119511
0.23887503311276
Approved
2022-08-11 06:39:15
ee1.eew
0
Room

Progress Update : 2022-05-13
Completed
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7244822,93.8119511
0.23887503311276
Approved
2022-08-11 06:38:51
ee1.eew
0
Room

Progress Update : 2021-09-29
In progress
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7225715,93.8107877
0.010417755636393
Approved
2021-10-17 10:18:10
ee1.eew
0
Back view

Progress Update : 2021-09-29
In progress
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7227197,93.8108965
0.01925035118538
Approved
2021-10-17 10:17:35
ee1.eew
0
Room

Progress Update : 2021-09-29
In progress
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7227056,93.8107284
0.0067032120807757
Approved
2021-10-17 10:16:34
ee1.eew
0
Verandah view

Progress Update : 2021-09-29
In progress
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7225486,93.8108291
0.015095777196465
Approved
2021-10-17 10:15:55
ee1.eew
0
Front view

Progress Update : 2020-03-06
Work in progress
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7231567,93.8114933
0.096247027605929
Approved
2020-03-16 09:57:47
ce.eew-mn
0
Back view

Progress Update : 2020-03-06
Work in progress
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7231567,93.8114933
0.096247027605929
Approved
2020-03-16 09:57:20
ce.eew-mn
0
Back view

Progress Update : 2020-03-06
Work in progress
Nil
sur1.eew-mn
24.722645427399318,93.81072432943037
24.7231567,93.8114933
0.096247027605929
Approved
2020-03-16 09:56:51
ce.eew-mn
0
Front view

Foundation & Inauguration
-
-
-

-
-
-