TBL/darpan/tblcourt/4
Construction of G+3 Annexe building for the Court of District & Sessions Judge at Thoubal
22/02/2016
PWD
Thoubal
1555.97
1356.49
CSS / CPS
100%
VI
24.625665067894033,94.01488351821922
Progress Update : 19/01/2023
100%
VI
9612527160
24.625665067894033,94.01488351821922
24.6258205,94.014637
0.030324091041091
1356.49
Premix carpeting of ground and approach road, finishing items

Progress Update : 19/01/2023
100%
VI
9612527160
24.625665067894033,94.01488351821922
24.6256812,94.0145251
0.036271987416669
1356.49
Premix carpeting of ground and approach road, finishing items

Progress Update : 19/01/2023
100%
VI
9612527160
24.625665067894033,94.01488351821922
24.6255371,94.0145218
0.039232356901136
1356.49
Premix carpeting of ground and approach road, finishing items

Progress Update : 19/01/2023
100%
VI
9612527160
24.625665067894033,94.01488351821922
24.6254295,94.0145316
0.044173911929566
1356.49
Premix carpeting of ground and approach road, finishing items

Progress Update : 24/02/2022
100%
V
9612527160
24.625665067894033,94.01488351821922
24.6254631,94.0151523
0.035247436372398
1356.49
Finishing items.

Progress Update : 24/02/2022
98%
V
9612527160
24.625665067894033,94.01488351821922
24.6263793,94.0150264
0.080717641369678
1058.16
Finishing items.

Progress Update : 19/03/2021
97%
IV
9612527160
24.625665067894033,94.01488351821922
24.6254683,94.0146231
0.034227630014749
835.936
Marble flooring, colouring and finishing items

Progress Update : 23/09/2019
78
III
9612527160
24.625665067894033,94.01488351821922
24.6250032,94.0154773
0.09496328620543
622.386
Brick walling and cement plastering is started

Progress Update : 23/09/2019
78
III
9612527160
24.625665067894033,94.01488351821922
24.6250032,94.0154773
0.09496328620543
622.386
Brick walling and cement plastering is started

Progress Update : 15/03/2019
65%
Phase III
9612527160
24.625665067894033,94.01488351821922
24.6258356,94.0146911
0.027162301519898
622.386
RCC frame structure completed

Progress Update : 15/03/2019
65%
Phase III
9612527160
24.625665067894033,94.01488351821922
24.5964531,94.0371237
3.9502496118757
622.386
RCC frame structure completed

Progress Update : 27/05/2018
ongoing
2
sotbl2
24.625665067894033,94.01488351821922
24.6383458,94.0022662
1.9011245199578
424.93
site photo

Progress Update : 27/05/2018
ongoing
2
sotbl2
24.625665067894033,94.01488351821922
24.6224893,94.016073
0.37301967283433
424.93
site photo

Progress Update : 23/05/2018
ongoing
2
sotbl2
24.625665067894033,94.01488351821922
24.6255933,94.01458
0.031699473323791
424.93
site photo

Progress Update : 23/05/2018
ongoing
2
sotbl2
24.625665067894033,94.01488351821922
24.6255733,94.01464
0.026645282183873
424.93
site photo

Progress Update : 02/11/2017
ongoing
1
sotbl2
24.625665067894033,94.01488351821922
24.6216944,94.0139151
0.45221809666849
0
site photo

Progress Update : 02/11/2017
ongoing
1
sotbl2
24.625665067894033,94.01488351821922
24.6273652,94.0138395
0.21649610280888
0
site photo