Project Details
DAR-2020-000223
BD-III/Mechanical office
Construction of Office and Workshop building for Mechanical Division No.-I & II at Kongba Lairenpat.
23/09/2017
PWD
Imphal-East
771.69
340.49
MH: 4059/01/051/11/10/53
Workshop - Completed, Office- Nearing completion
Phase 4
24.7764476,93.97018059999999
Constn. of G+1 RCC framed structure & tubular trusses workshop,etc.
Progress Update : 18/10/2024
Workshop - Completed, Office- Nearing completion
Phase 4
7085206407
24.7764476,93.97018059999999
24.7743003,93.9710866
0.25567760822814
340.489
WORKSHOP- Plastering, Tiling, Painting, Plinth Protection, SOUTH BLOCK- Tiling, Plastering, Painting, Pipe Fittings, NORTH BLOCK- RCC Slab Casting, Plastering, Brickwork, Woodwork

Progress Update : 01/02/2024
In progress
3
7085206407
24.7764476,93.97018059999999
24.7728194,93.9715674
0.42702193650912
224.19
Front elevation and Interior view of South Block

Progress Update : 01/02/2024
In progress
3rd
7085206407
24.7764476,93.97018059999999
24.7728218,93.9715709
0.42688589997314
224.19
Front elevation and Interior view of South Block

Progress Update : 01/02/2024
In progress
3rd
7085206407
24.7764476,93.97018059999999
24.7804053,93.9698279
0.4414931393213
224.19
Front elevation and Interior view of South Block

Progress Update : 27/02/2023
In progress
Phase 2
7308531672
24.7764476,93.97018059999999
24.7742267,93.9710373
0.26164881248792
140.2
PWD Mechanical Office South Block

Progress Update : 27/02/2023
In Progress
Phase 2
7308531672
24.7764476,93.97018059999999
24.7744635,93.971062
0.23788048111056
140.2
Mechanical Office Building North Block

Progress Update : 24/11/2022
In progress
Phase 2
7308531672
24.7764476,93.97018059999999
24.77416468,93.97102217
0.26767809843603
140.2
Mechanical Division Office Building South Block

Progress Update : 24/11/2022
In progress
Phase2
7308531672
24.7764476,93.97018059999999
24.77418977,93.97107769
0.26688368117243
140.2
Mechanical Division Office North Block

Progress Update : 24/11/2022
In progress
Phase 2
7308531672
24.7764476,93.97018059999999
24.77435611,93.97101495
0.2473366943694
140.2
Mechanical Workshop

Progress Update : 21/11/2020
In Progress
1
7308531672
24.7764476,93.97018059999999
24.7778128,93.9698279
0.15591617507726
0
PWD Mechanical Division Office Building South Block

Progress Update : 21/11/2020
In Progress
1
7308531672
24.7764476,93.97018059999999
24.7741013,93.9710476
0.27517581198037
0
PWD Mechanical Division Office Building South Block

Progress Update : 21/11/2020
In Progress
1
7308531672
24.7764476,93.97018059999999
24.774241,93.9710362
0.26011179543767
0
PWD Mechanical Division Office Building North Block

Progress Update : 21/11/2020
In Progress
1
7308531672
24.7764476,93.97018059999999
24.7743828,93.9710312
0.2451184075334
0
PWD Mechanical Division workshop Building perspective veiw

Progress Update : 22/07/2020
In progress
1
9862132527
24.7764476,93.97018059999999
24.77444369,93.97101483
0.23819957166423
0
PWD Mechanical Workshop Foundation and Columns steel erection

Progress Update : 22/07/2020
In progress
1
9862132527
24.7764476,93.97018059999999
24.77418728,93.97102364
0.26534392449444
0
PWD Mechanical Office Building

Progress Update : 03/03/2020
In progress
1
9862132527
24.7764476,93.97018059999999
24.77411516,93.9710497
0.27378309062341
0
For one block column work under progress till first floor level