Progress
 
 
Project Details
PD/EAP/Sports-Univ/2017
Construction of Helipad, Meeting Venue, Impt. of road and barricading for laying of Foundation Stone of the National Sports University.
2017-07-13
PWD
Imphal-West
350.00
0.00
State Plan
Completed
I
24.897069444444444,93.82956944444445
The Department undertake preparatory works including Construction of Helipad, Meeting Venue, Improvement of road from Helipad to Meeting Venue and barricading in connection with the visit of the Hon’ble Prime Minister of India in Manipur for laying of Foundation Stone of the National Sports University. The work has been accorded Administrative Approval and Expenditure Sanction amounting to ₹ 3,50,06,700/- vide No. 32/11/2017-W dt. 13.07.2017 under MH : 5054 C.O Roads and Bridges (Plan) to meet the above expenditures.
Progress Update : 2017-10-24
Completed
I
eapso1
24.897069444444444,93.82956944444445
24.9050593,93.8341403
1.0008701216675
Approved
2017-11-27 11:09:53
eapmanipur
0
Construction of Helipad, Meeting Venue i/c impt. of road from Helipad to Meeting Venue and barricading in connection with the visit of the Hon'ble Prime Minister of India in Manipur for laying Foundation stone of Sports University. SH: Construction of Helipad.

Progress Update : 2017-10-24
Completed
I
eapso1
24.897069444444444,93.82956944444445
24.9050593,93.8341403
1.0008701216675
Approved
2017-10-26 08:39:09
eapmanipur
0
Construction of Helipad, Meeting Venue i/c impt. of road from Helipad to Meeting Venue and barricading in connection with the visit of the Hon'ble Prime Minister of India in Manipur for laying Foundation stone of Sports University. SH: Construction of Helipad.

Progress Update : 2017-10-24
Complete.
Phase-I
eapso2
24.897069444444444,93.82956944444445
24.8968907,93.8297836
0.02935171607444
Approved
2017-10-25 10:06:05
eapmanipur
0
Parking for VIP

Foundation & Inauguration
-
-
-

-
-
-