Progress
 
 
Project Details
DAR-2020-000170
MID-NESIDS(FDR)-2019-20-Kharkhola
Re-Construction of Pick-up Weir a/c Haipi stream at Kharkhola.
2019-08-05
Minor Irrigation Department
Kangpokpi
64.47
0.00
CSS / CPS
Ongoing
1
25.11777778,93.94833333
Progress Update : 2020-02-13
Ongoing
1
midie02
25.11777778,93.94833333
25.1110579,93.9544262
0.96672644173943
Approved
2020-02-14 05:00:59
eemid4
0
Pick up weir and canal

Foundation & Inauguration
-
-
-

-
-
-