Progress
 
 
Project Details
DAR-2020-000107
MOBEDS/5/SM/Kamjong
Construction of Sadhavna Mandav/Sadhavna Mandap at Kamjong TD BLock
2017-11-30
MOBC
Ukhrul
250.00
21.00
CSS / CPS
Work progress
1st phase
24.857775908382024,94.51467829942717
Progress Update : 2020-02-04
Work progress
1st phase
mobeds_ap
24.857775908382024,94.51467829942717
24.85932776,94.5160185
0.21921468758894
Approved
2020-02-24 11:06:25
mobcadmin
0
Sadhvana Mandap

Progress Update : 2020-02-04
Work progress
1st phase
mobeds_ap
24.857775908382024,94.51467829942717
24.85932776,94.5160185
0.21921468758894
Approved
2020-02-24 11:07:13
mobcadmin
0
Sadhvana Mandap

Progress Update : 2020-02-04
Work progress
1st phase
mobeds_ap
24.857775908382024,94.51467829942717
24.85932776,94.5160185
0.21921468758894
Approved
2020-02-24 11:08:35
mobcadmin
0
Sadhvana Mandap

Foundation & Inauguration
-
-
-

-
-
-