Progress
 
 
Project Details
DAR-2019-000587
KCG/DARPAN/ROAD(P)/01
Impvt of road at Hiyanglam A/C.
08/03/2019
PWD
Kakching
150.00
126.50
MH
100%
2nd& final
24.494686705169155,93.93836965659182
Shingling,WBM,PC,etc.
Progress Update : 13/03/2020
100%
2nd& final
9862139630
24.494686705169155,93.93836965659182
24.5009608,93.9449684
0.96562719335871
126.5
WBM &PC

Progress Update : 13/03/2020
100%
2nd& final
9862139630
24.494686705169155,93.93836965659182
24.5037789,93.936366
1.0310834786146
126.5
WBM &PC

Progress Update : 13/03/2020
100%
2nd& final
9862139630
24.494686705169155,93.93836965659182
24.5037789,93.936366
1.0310834786146
126.5
WBM &PC

Progress Update : 13/03/2020
100%
2nd& final
9862139630
24.494686705169155,93.93836965659182
24.5037789,93.936366
1.0310834786146
126.5
WBM &PC

Progress Update : 13/03/2020
100%
2nd& final
9862139630
24.494686705169155,93.93836965659182
24.5112247,93.9350916
1.8685228034887
126.5
WBM &PC

Progress Update : 07/01/2020
40%
First
7085631665
24.494686705169155,93.93836965659182
24.506744,93.936366
1.3558863884052
126.5
WBM

Progress Update : 07/01/2020
40%
First Phase
7085631665
24.494686705169155,93.93836965659182
24.4976939,93.9375729
0.34394986260242
126.5
WBM & PC

Progress Update : 07/01/2020
40%
First Phase
7085631665
24.494686705169155,93.93836965659182
24.5007227,93.9398705
0.68810507164718
126.5
WBM & PC

Progress Update : 07/01/2020
40%
First Phase
7085631665
24.494686705169155,93.93836965659182
24.5072583,93.9409073
1.4212147199073
126.5
WBM

Progress Update : 07/01/2020
40%
First Phase
7085631665
24.494686705169155,93.93836965659182
24.5072583,93.9409073
1.4212147199073
126.5
WBM