Progress
 
 
Project Details
UKL/TNL-NH150/2
Construction of road from TNL ground to NH-150 via Kahumtang and BRTF
21/03/2013
PWD
Ukhrul
400.00
385.82
State Plan
Improvement
Phase
25.096907565385703,94.37701340802619
Earthwork, RCC Slab culvert, Retaining Wall, B/Wall
Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10841407,94.36616579
1.6822067023836
0
Earth work, PC, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10647642,94.3699857
1.2777771706495
0
Earth work, PC, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10080703,94.36868068
0.94443662182282
0
Earth work, PC, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10080703,94.36868068
0.94443662182282
0
Earth work, PC, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10080703,94.36868068
0.94443662182282
0
Earth work, PC, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10080703,94.36868068
0.94443662182282
0
Earth work, PC, WBM, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10080703,94.36868068
0.94443662182282
0
Earth work, PC, WBM, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10080703,94.36868068
0.94443662182282
0
Earth work, PC, WBM, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10080703,94.36868068
0.94443662182282
0
Earth work, PC, WBM, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.10096346,94.36865669
0.95467497413047
0
Earth work, PC, WBM, RW & BW

Progress Update : 08/09/2017
Improvement
Phase
eeukld
25.096907565385703,94.37701340802619
25.1034709,94.3617595
1.7004683167032
0
Earth work, PC, WBM, RW & BW

Progress Update : 13/08/2017
Completed
Phase I
eeukld
25.096907565385703,94.37701340802619
25.1006883,94.3685421
0.95094560270523
0
Breast wall, R/wall, Culverts, Premix

Progress Update : 13/08/2017
Completed
Phase I
eeukld
25.096907565385703,94.37701340802619
25.1289879,94.3698422
3.6393339848397
0
Breast wall, R/wall, Culverts, Premix

Progress Update : 13/08/2017
Completed
Phase I
eeukld
25.096907565385703,94.37701340802619
25.1058473,94.3643816
1.6142259460291
0
Breast wall, R/wall, Culverts, Premix

Progress Update : 13/08/2017
Completed
Phase I
eeukld
25.096907565385703,94.37701340802619
25.0936225,94.365024
1.2613050119374
0
Breast wall, R/wall, Culverts, Premix

Progress Update : 13/08/2017
Completed
Phase I
eeukld
25.096907565385703,94.37701340802619
25.0965416,94.3665777
1.051585192584
0
Breast wall, R/wall, Culverts, Premix

Progress Update : 13/08/2017
Completed
Phase I
eeukld
25.096907565385703,94.37701340802619
25.0936225,94.365024
1.2613050119374
0
Breast wall, R/wall, Culverts, Premix