Progress
 
 
Project Details
DAR-2019-000438
NESIDS SPT HQ
Augmentation of Senapati District Head Quarter Water Supply Scheme for promoting tourism
13/12/2018
PHED
Senapati
3584.53
0.00
NESIDS
Ongoing project
Phase ¹
25.315792537459828,94.06704711914085
Progress Update : 04/03/2021
Ongoing project
Phase ¹
Lohrii
25.315792537459828,94.06704711914085
25.3175324,94.0665841
0.19897361100799
0
Pump house at Barak river

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3168009,94.0674771
0.12016048232139
0
Pump house

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3170267,94.0673514
0.14059279653587
0
Pump house

Progress Update : 04/03/2021
Ongoing project
Phase ¹
Lohrii
25.315792537459828,94.06704711914085
25.3164187,94.0685931
0.17027294618562
0
Black topping of approach road

Progress Update : 04/03/2021
Ongoing project
Phase ¹
Lohrii
25.315792537459828,94.06704711914085
25.3166194,94.0688204
0.2005497455729
0
Chowkidar quarter

Progress Update : 04/03/2021
Ongoing project
Phase ¹
Lohrii
25.315792537459828,94.06704711914085
25.3162006,94.068643
0.16669766005245
0
Black topping of approach road

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3159097,94.0693019
0.22700530156092
0
Retaking wall

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3160253,94.0700769
0.30562517832591
0
Slow Sand Filter

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3159992,94.0707717
0.37506730390992
0
Pipe support

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3161764,94.0704699
0.34666566012678
0
Pipe support

Progress Update : 04/03/2021
Ongoing
Phase1
Lohrii
25.315792537459828,94.06704711914085
25.3090662,94.0441591
2.4190873775622
0
SSF

Progress Update : 04/03/2021
Ongoing pr9ject
Phase ¹
Lohrii
25.315792537459828,94.06704711914085
25.3159183,94.0695457
0.25152484211866
0
Settling Tank

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3160316,94.0694406
0.24203605784023
0
Aerator

Progress Update : 04/03/2021
Ongoing project
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.2713704,94.0223681
6.6761313848208
0
Main zonal reservoir

Progress Update : 01/06/2020
In progress
Phase1
Lohrii
25.315792537459828,94.06704711914085
25.2520353,94.0086239
9.2063462473361
0
Zonal Reservoir at poumai taphou

Progress Update : 01/06/2020
In progress
Phase1
Lohrii
25.315792537459828,94.06704711914085
25.261734,94.0170302
7.8366967148582
0
Zonal Reservoir lower taphou

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3042072,94.0460746
2.4705013132437
0
Stacking of pipes for besides spt.

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3013277,94.0432013
2.8865178701832
0
Stacking of pipes for besides spt.

Progress Update : 01/06/2020
In progress
Phase1
Lohrii
25.315792537459828,94.06704711914085
25.3176473,94.0661979
0.22319609799043
0
Intake type at barakvriver

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3023584,94.0460746
2.5836627437888
0
Stacking of pipes for besides spt.

Progress Update : 01/06/2020
In progress
Phase1
Lohrii
25.315792537459828,94.06704711914085
25.3078697,94.0473516
2.1668462077819
0
L/f of pipe line

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3067692,94.0470324
2.2480849074377
0
Laying of pipeline

Progress Update : 01/06/2020
In progress
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3894763,94.0870131
8.4349210409816
0
Approach road1

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3016887,94.0435206
2.8375402967165
0
Service reservoir

Progress Update : 01/06/2020
In progress
Phase1
Lohrii
25.315792537459828,94.06704711914085
25.3134507,94.0460746
2.1240199561747
0
Approach road

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3240706,94.0767324
1.3397018475663
0
Trace path cutting and laying of raw main pipe line

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3240706,94.0767324
1.3397018475663
0
Trace path cutting and laying of raw main pipe line

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3720633,94.1058101
7.3701625344763
0
Treatment plant

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3127074,94.0326675
3.4725742840063
0
Approach road

Progress Update : 01/06/2020
Ongoing project
Phase-1
jameson
25.315792537459828,94.06704711914085
25.3016887,94.0435206
2.8375402967165
0
Land development

Progress Update : 01/06/2020
In progress
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3159804,94.0697622
0.2736947792165
0
Slow sand filter

Progress Update : 01/06/2020
In progress
Phase 1
Lohrii
25.315792537459828,94.06704711914085
25.3078697,94.0473516
2.1668462077819
0
Settling tank

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3204013,94.0494861
1.8379343779252
0
Service Reservoir

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.316184,94.0690202
0.20303732630767
0
Service Reservoir

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3158669,94.0693599
0.23260791499072
0
Approach Rd.

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3159605,94.0696672
0.26400934227866
0
Approach Rd.

Progress Update : 31/08/2019
in progress
single phase
hjoy
25.315792537459828,94.06704711914085
25.3161285,94.069338
0.23326989824696
0
Steep cutting of earthwork

Progress Update : 31/08/2019
in progress
single phase
hjoy
25.315792537459828,94.06704711914085
25.316051,94.0694284
0.2410649035114
0
Aerial view of Service Reservoir

Progress Update : 31/08/2019
in progress
single phase
hjoy
25.315792537459828,94.06704711914085
25.3204013,94.0494861
1.8379343779252
0
concrete stacking

Progress Update : 31/08/2019
in progress
single phase
hjoy
25.315792537459828,94.06704711914085
25.3159191,94.069402
0.23711036154005
0
Steel bars stacking for SSF.

Progress Update : 31/08/2019
in progress
single phase
hjoy
25.315792537459828,94.06704711914085
25.3159357,94.0696101
0.2581001415985
0
Matterials stacking for SSF

Progress Update : 31/08/2019
in progress
single phase
hjoy
25.315792537459828,94.06704711914085
25.3159571,94.0696659
0.26385251565043
0
Matterials stacking for SSF

Progress Update : 31/08/2019
in progress
single phase
hjoy
25.315792537459828,94.06704711914085
25.3159326,94.0696818
0.2652730005244
0
Matterials stacking for SSF

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.316151,94.0698455
0.28407887485374
0
slow sand fiter . steep wall on hill side

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3160536,94.0698559
0.28380271851367
0
slow sand fiter . steep wall on hill side

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3160393,94.0696619
0.26424348689019
0
slow sand fiter . steep wall on hill side

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3162014,94.0696112
0.261698008998
0
slow sand fiter earth work

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3161129,94.069458
0.24492496428261
0
settling tank

Progress Update : 31/08/2019
in progress
single
hjoy
25.315792537459828,94.06704711914085
25.3159428,94.0696246
0.25960439433541
0
settling tank

Progress Update : 30/08/2019
Ongoing
Single
thole
25.315792537459828,94.06704711914085
25.31611138,94.06930448
0.22964334331856
0
Service Reservoir