Progress
 
 
Project Details
10(1)/2015-SD/MQCD/TSM/Kangla/Platform/25
Development of Tourist Circuit in Manipur..........(SH: Construction of Dance Performance platform in front of Shri Shri Govindaji Temple)
29/06/2015
PWD
Imphal-West
209.94
97
Ministry of Tourism, GOI
Completed
Final
24.80639929552795,93.9447115659716
Construction of Dance performance platform (Mandap) using wooden structures, thatch roof, earthen gallery including Green room and toilet etc
Progress Update : 05/02/2021
Completed
Final
aemqcd1
24.80639929552795,93.9447115659716
24.8088525,93.9443311
0.27546045357371
97
Dance performance

Progress Update : 06/09/2019
Ongoing
4
aemqcd1
24.80639929552795,93.9447115659716
24.8058312,93.9465616
0.19711951886767
65.236
Polishing work of structural timber members of Dance Performance Platform at Kangla

Progress Update : 25/10/2018
Ongoing
3
aemqcd1
24.80639929552795,93.9447115659716
24.8065552,93.9471989
0.25164471477076
78.225
Undergoing thatch roofing of Dance Performance Platform at Kangla

Progress Update : 25/10/2018
Ongoing
3
aemqcd1
24.80639929552795,93.9447115659716
24.8065552,93.9471989
0.25164471477076
78.225
Undergoing thatch roofing of Dance Performance Platform at Kangla