Progress
 
 
Project Details
NH-I/GOM/2017-18/02
Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 245.00 and km 260.00 during 2017-18
25/06/2015
PWD
Senapati
17.22
0.00
Fund deposited by Dishnet Wireless Lld, Guwahati
Completed
Completed
25.3003,94.04180277777778
Resectioning of drain and side berm
Progress Update : 17/08/2017
Completed
Completed
nh1so1a
25.3003,94.04180277777778
25.337751666667,94.056185
4.4079969598624
0
Clearance of side berm and drain

Progress Update : 14/08/2017
COMPLETED
COMPLETED
nh1so1a
25.3003,94.04180277777778
25.2463659,94.010968
6.750925577036
0
Drain and side berm clearance