Progress
 
 
Project Details
DAR-2018-001379
WP/18-NCC-DMC-IW
Improvement of Existing Infrastructure of NCC Office at D.M. College Campus, Imphal
2018-03-19
Education (S)
Imphal-West
23.70
0.00
State Plan
Completed
Nill
24.819704343979488,93.93973070383083
Improvement of Existing Infrastructure of NCC Office at D.M. College Campus, Imphal
Progress Update : 2019-01-25
Completed
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.8186065,93.9395519
0.12339538063621
Approved
0
Overhead Tank

Progress Update : 2019-01-25
Completed
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.8186065,93.9395519
0.12339538063621
Approved
2019-02-06 11:34:50
ce.eew-mn
0
Water reservoir

Progress Update : 2018-10-28
In progess
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.820135,93.9397667
0.048022190472501
Approved
2018-11-02 12:37:53
ce.eew-mn
0
Septic tank

Progress Update : 2018-10-28
In progess
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.8201533,93.93975
0.049957291312907
Approved
2018-11-02 12:38:04
ce.eew-mn
0
Toilet repairing

Progress Update : 2018-10-28
In progess
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.81976,93.9398783
0.016129845777053
Approved
2018-11-02 12:38:13
ce.eew-mn
0
Girls bathroom

Progress Update : 2018-10-28
In progess
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.8197583,93.939665
0.0089426562119239
Approved
2018-11-02 12:38:24
ce.eew-mn
0
Overhead tank

Progress Update : 2018-10-28
In progess
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.820035,93.9398183
0.037813306407101
Approved
2018-11-02 12:39:08
ce.eew-mn
0
Septic tank

Progress Update : 2018-10-28
In progess
Nill
sur1.eew-mn
24.819704343979488,93.93973070383083
24.8203267,93.9398933
0.07111838810714
Approved
2018-11-02 12:38:36
ce.eew-mn
0
Kitchen /store room

Foundation & Inauguration
-
-
-

-
-
-